J. Slotnik Company
Project Owner
Town of Duxbury – Duxbury Free Library
Project Description
The project consisted of the renovation of an existing school into a library. The 36,000 sf school building posessed two story above grade and one story below grade.
Project Cost and Duration
Estimated $4.7 Million and twelve (12) months duration.
Responsibilities
As part of the general contractor’s team, J. Slotnik Company, Peña Alcántara Consultants developed the As-Planned CPM schedule for the school project. covering all construction submittals, procurement, purchases, mock-ups, sample testing and construction activities in addition to the integration of the Subcontractors schedules: Masonry, Roofing, etc..
In addition Peña Alcántara Consultants’ responsibilities included the monthly development and issuance of a 6-week lookahead schedule, presentation of regular updates/analyses and evaluation of progress.
Analytical Tools
Primavera for Windows
![](https://i0.wp.com/pena-alcantara.com/wp-content/uploads/2018/05/b62e630b594d53f538f0b54416372419_-united-states-massachusetts-plymouth-county-duxbury-alden-street-77-duxbury-free-library-781-934-2721.jpg?resize=1024%2C665)