J. Slotnik Company
Project Owner
Town of Duxbury – Duxbury Free Library
Project Description
The project consisted of the renovation of an existing school into a library. The 36,000 sf school building posessed two story above grade and one story below grade.
Project Cost and Duration
Estimated $4.7 Million and twelve (12) months duration.
Responsibilities
As part of the general contractor’s team, J. Slotnik Company, Peña Alcántara Consultants developed the As-Planned CPM schedule for the school project. covering all construction submittals, procurement, purchases, mock-ups, sample testing and construction activities in addition to the integration of the Subcontractors schedules: Masonry, Roofing, etc..
In addition Peña Alcántara Consultants’ responsibilities included the monthly development and issuance of a 6-week lookahead schedule, presentation of regular updates/analyses and evaluation of progress.
Analytical Tools
Primavera for Windows